Control of Raw Material Inventories N-108 and L-107 Using the Material Requirements Planning Method
DOI:
https://doi.org/10.59976/jurit.v4i3.421Keywords:
Inventory Control, Material Requirements Planning, Lot Sizing, Period Order Quantity, Total Inventory Cost.Abstract
This study evaluates inventory policies for N-108 and L-107, two raw materials used in emulsion paint and paper resin production. It identifies the ordering method with the lowest inventory cost while meeting material requirements from January to June 2026. Monthly opening stocks, receipts and usage were checked against recorded closing stocks. Three-period moving average (MA-3) and single exponential smoothing (SES) forecasts were compared over April–June. Lot-for-lot (LFL), economic order quantity (EOQ) and period order quantity (POQ) were then evaluated using historical warehouse issues, safety stock and a one-month lead time. Historical issues served as gross requirements because production schedules and material coefficients were unavailable. The six-month usage was 1,959 kg for N-108 and 2,631 kg for L-107. SES gave the lower forecast error for N-108 and predicted 247.26 kg for July. MA-3 gave the lower error for L-107 and predicted 422.33 kg. The operational EOQ lots were 724 and 839 kg, and safety stocks were 120 and 214 kg, respectively. N-108 required no purchases, whereas POQ called for three L-107 receipts totaling 1,917 kg. Combined six-month inventory costs were Rp5,018,943 under POQ, Rp5,280,702 under LFL and Rp5,466,062 under EOQ. POQ retained the lowest cost in all twelve sensitivity scenarios. The results support a two-month ordering interval for L-107 within the study horizon. The modeled reduction of 54.44% relative to reconstructed warehouse practice depends on the assumed order counts and allocated holding cost.
References
W. J. Kurniawan, E. Sutomo, and E. Rahmawati, “Application of the Material Requirement Planning (MRP) Method for Raw Material Control Planning at PT. XYZ,” UNIS J. Comput. Eng., vol. 11, no. 1, pp. 83–93, 2023, doi: 10.33592/jutis.v11i1.3267.
M. R. Ficroni and E. Ismiyah, “Strategi Pengendalian Persediaan Bahan Baku Kain Tas Menggunakan Metode EOQ dan POQ (Studi Kasus: CV. SMY),” J. Teknol. dan Manaj. Ind. Terap., vol. 5, no. 2, pp. 1217–1225, 2026, doi: 10.55826/jtmit.v5i2.1875.
M. Schlenkrich and S. N. Parragh, “Capacitated multi-item multi-echelon lot sizing with setup carry-over under uncertain demand,” Int. J. Prod. Econ., vol. 277, 2024, doi: 10.1016/j.ijpe.2024.109379.
S. E. Gulo, A. Hura, M. S. D. Mendrofa, and D. Lase, “Analisis Penerapan Metode Material Requirement Planning (MRP) dalam Perencanaan Persediaan Bahan Baku pada Produksi Kue di Wery Bakery,” Innov. J. Soc. Sci. Res., vol. 3, no. 4, pp. 5729–5739, 2023, [Online]. Available: https://j-innovative.org/index.php/Innovative/article/view/4190
F. D. Utami and E. Widajanti, “Analisis Pengendalian Persediaan Bahan Baku dengan Menggunakan Metode Material Requirement Planning pada Industri Tempe Pak Parmin di Karanganyar,” J. Ekon. Manaj. dan Bisnis, vol. 2, no. 1, pp. 631–640, 2024, doi: 10.62017/jemb.v2i1.2257.
T. Achla, E. D. Priyana, and Y. P. Negoro, “A Comparison of Inventory Control Analyses for Consumable Goods Using the Min-Max and EOQ Methods at General Trading Supplier UD. Hasta Jaya,” G-Tech J. Teknol. Terap., vol. 8, no. 4, pp. 2622–2631, 2024, doi: 10.70609/gtech.v8i4.5387.
N. L. P. W. Widyastari, I. M. D. B. Penindra, B. E. I. Sitanggang, A. A. I. A. S. Komaladewi, M. Juliana, and N. M. C. Utami, “Analisis Material Requirement Planning dalam Pengendalian Persediaan Bahan Baku pada PT X,” J. Ris. dan Apl. Tek. Ind., vol. 3, no. 1, 2025, doi: 10.24843/JRATI.2025.v03.i01.p07.
A. N. R. Nuryadi and M. Jufriyanto, “Analisis Peramalan Kebutuhan Bahan Baku BA 1 Menggunakan Metode Moving Average dan Single Eksponential Smoothing,” J. Teknol. dan Manaj. Ind. Terap., vol. 3, no. I, pp. 831–839, 2026, doi: 10.55826/jtmit.v5i2.1738.
S. F. Lopenzo, Jesen, and R. S. Nasution, “Analisis Perbandingan Metode EOQ POQ dalam Perencanaan Pengendalian Persediaan Retail Toko A,” Greeners J. Green Eng. Sustain., vol. 1, no. 2, pp. 78–90, 2024, doi: 10.63643/jges.v1i2.211.
F. Hermawan, Sumarsono, N. Muflihah, and F. A. N. F. Afiatna, “Analisis Perencanaan Bahan Baku Menggunakan Material Requirement Planning dengan Perbandingan Beberapa Lot Sizing: Studi Kasus UKM Tahu,” J. Penelit. Bid. Inov. Pengelolaan Ind., vol. 5, no. 2, pp. 32–46, 2026, doi: 10.33752/invantri.v5i2.9783.
R. Kurniawan and E. Ismiyah, “Analisis Persediaan Bahan Kimia Karl Fisher Solvent Pada PT. XYZ dengan Metode Economic Order Quantity (EOQ) dan Periodic Order Quantity (POQ),” G-Tech J. Teknol. Terap., vol. 8, no. 4, pp. 2668–2674, 2024, doi: 10.70609/gtech.v8i4.5421.
T. Prastomo and R. A. Rahma, “Analysis of Raw Material Inventory Planning for SCZ-Type Motor Chains Using the Material Requirements Planning Method,” STRING (Satuan Tulisan Ris. dan Inov. Teknol., vol. 9, no. 2, p. 204, 2024, doi: 10.30998/string.v9i2.25910.
N. Sujana, “Analysis of Raw Material Management Using the Material Requirements Planning Method to Improve Inventory Cost Efficiency (A Study of the Keramat Sanga-Sanga Amplang Small and Medium Enterprise),” J. Bus. Adm. FISIPOL UNMUL, vol. 11, no. 1, pp. 77–84, 2023, [Online]. Available: http://e-journals.unmul.ac.id/index.php/jadbis/index
A. F. Ridwan and M. Ahsan, “Determination of Reorder Points and Safety Stock for Consumable Materials Based on Forecasting Using an Artificial Neural Network,” J. Rekayasa Ind., vol. 6, no. 1, pp. 51–61, 2024, doi: 10.37631/jri.v6i1.1220.
C. Gunawan, D. Kodrat, and T. Christian, “Engine Oil Inventory Management: Comparative Study of Lot-Sizing Methods and Managerial Decision Framework under Cashflow Constraints,” J. Manaj. Teknol., vol. 25, no. 1, pp. 37–64, 2026, doi: 10.12695/jmt.2026.25.1.3.
T. Setianto, L. T. Harinie, A. Syamsudin, and J. Giovanni, “Implementation of Material Requirements Planning for Raw Material Inventory Control in Home Industry Palangka Raya,” JURISMA J. Ris. Bisnis Manaj., vol. 15, no. 1, 2025, doi: 10.34010/ybk4h960.
J. F. Sari, H. Hidayat, and Y. P. Negoro, “Implementation of the Material Requirements Planning (MRP) Method in Raw Material Control at CV. D BY MITARASA,” INTECOMS J. Inf. Technol. Comput. Sci., vol. 7, no. 6, pp. 2228–2240, 2024, doi: 10.31539/intecoms.v7i6.12896.
A. Purnomo and Syafrianita, “Incorporating Time Value of Money into Lot-Sizing Decisions for Improved Supply Chain Performance,” J. Syst. Manag. Sci., vol. 14, no. 3, pp. 514–532, 2024, doi: 10.33168/JSMS.2024.0330.
H. Srour and A. Azmy, “Inventory Management and Its Impact on the Firm Performance,” World Res. Bus. Adm. J., vol. 1, no. 1, 2021, doi: 10.56830/WRBA11202103.
G. L. Sumpeno, R. S. Harjanti, and A. Yasmin, “Rekonseptualisasi Pengelolaan Persediaan Bahan Baku melalui Pendekatan Material Requirement Planning pada Industri Manufaktur,” Inkubis J. Ekon. dan Bisnis, vol. 7, no. 2, pp. 119–130, 2025, doi: 10.59261/inkubis.v7i2.97.
V. Nurcahyawati, R. A. Brahmantyo, and J. Wibowo, “Inventory Management Using the Safety Stock and Reorder Point Methods,” J. Sains dan Inform., vol. 9, no. 1, pp. 89–99, 2023, doi: 10.34128/jsi.v9i1.431.
Suparno, N. Izzah, A. Rufaidah, and Narto, “Optimasi Pengendalian Bahan Baku Phospat Menggunakan Metode Economic Order Quantity (EOQ) dan Periodic Order Quantity (POQ) di PT XYZ,” J. Optim., vol. 12, no. 1, 2026, [Online]. Available: https://jurnal.utu.ac.id/joptimalisasi/article/view/14798
W. Kusnandi, L. Syaipudin, and A. Luthfi, “Strategi Penjualan dan Pemasaran dalam Bisnis Dagang Retail di Toko Agung Jaya Kunir Wonodadi Blitar,” J. Ilm. Ekon. Mod. dan Tradis., vol. 1, no. 1, pp. 1–13, 2024, doi: 10.61166/jiemt.v1i1.2.
I. K. Ramadhani, N. H. Ahmad, A. P. P. Purba, R. Marmay, and A. P. Hermanto, “Perencanaan Kebutuhan Material dengan Mempertimbangkan Kebijakan Persediaan LFL, MOQ, dan EOQ di CV Ayu Perabot Padang,” Matrik J. Manaj. dan Tek. Ind. Produksi, vol. 26, no. 2, pp. 223–240, 2026, doi: 10.30587/matrik.v26i2.11338.
Hartono and D. A. S. Prabowo, “Raw Material Inventory Control to Support the Smooth Production Process of the A-5828 Filter (A Case Study in the Automotive Components Industry),” J. Ind. Manuf., vol. 8, no. 1, p. 1, 2023, doi: 10.31000/jim.v8i1.8080.
Nurhasanah, R. F. Sari, and H. Cipta, “Pengendalian Persediaan Bahan Baku Brownies dengan Analisis Perbandingan Metode Min-Max, Economic Order Quantity dan Period Order Quantity,” J. Lebesgue J. Ilm. Pendidik. Mat. Mat. dan Stat., vol. 4, no. 1, pp. 151–160, 2023, doi: 10.46306/lb.v4i1.225.
N. Faurizka and P. A. Wicaksono, “Pengendalian Persediaan Bahan Baku pada Pengolahan Bahan Keramik dengan Metode EOQ dan POQ (Studi Kasus pada PT Sango Ceramics Indonesia),” Ind. Eng. Online J., vol. 13, no. 3, 2024, [Online]. Available: https://ejournal3.undip.ac.id/index.php/ieoj/article/view/45412
E. P. Meilani and F. N. Azizah, “Perbandingan Efektivitas Metode EOQ dan JIT dalam Pengelolaan Persediaan pada PT XYZ,” STRING (Satuan Tulisan Ris. dan Inov. Teknol., vol. 7, no. 3, p. 276, 2023, doi: 10.30998/string.v7i3.14585.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Amelia Nur Aini, Elly Ismiyah, Yanuar Pandu Negoro

This work is licensed under a Creative Commons Attribution 4.0 International License.
This work is licensed under a Creative Commons Attribution 4.0 International License (CC BY 4.0).